For a certain kind of plaster work, 1.9 cu yd of sand are needed for every 100 sq yd of surface. How much sand will be needed for 370 sq yd of surface? \( \square \) cu yd of sand will be needed for 370 sq yd of surface. (Simplify your answer.)
Real Tutor Solution
Answer
Solution
Sign in to Unlock Answers for Free!
A Learning Platform Trusted by Millions of Real Students and Teachers.
Reviewed and approved by the UpStudy tutoring team
Bonus Knowledge
To find out how much sand is needed for 370 sq yd of surface, you can set up a proportion based on the given information. Since 1.9 cu yd of sand is required for every 100 sq yd, you can use the formula: \[ \text{Sand needed} = \left(\frac{1.9 \, \text{cu yd}}{100 \, \text{sq yd}}\right) \times 370 \, \text{sq yd} \] Calculating this gives: \[ \text{Sand needed} = \frac{1.9 \times 370}{100} = 7.03 \, \text{cu yd} \] So, 7.03 cu yd of sand will be needed for 370 sq yd of surface.